By Matthew Brown

Amplify Energy’s emergency response plan for a major oil spill like the one it’s now dealing with in coastal Southern California depended heavily on a quick shutdown of the San Pedro Bay Pipeline if its sensors picked up a sudden loss of pressure. That’s not what happened, investigators revealed Tuesday.

After an alarm went off in a company control room at 2:30 a.m. Saturday — signaling a rupture that would spill tens of thousands of gallons of crude into the Pacific Ocean — the company waited more than three hours to shut down the pipeline, at 6:01 a.m., according to preliminary findings of an investigation into the spill.

The Houston-based company took another three hours to notify the U.S. Coast Guard's National Response Center for oil spills, investigators said, further slowing the response to an accident for which Amplify workers spent years preparing.

“How come it took so long? That’s a fair question,” said Richard Kuprewicz, a pipeline consultant and private accident investigator from Redmond, Washington. “If you have any doubt, your action should be to shut down and close. ... Something’s not quite right here.”

Pipeline control room alarms don’t always mean a leak and can be tripped by numerous factors — from a faulty signal from a sensor along the line, to a pump that goes offline and causes a sudden pressure change, according to Kuprewicz and other industry experts. But the alarms also are supposed to trigger immediate follow-up actions to quickly ascertain if anything is wrong.

It’s uncertain why that process dragged out hours in San Pedro Bay, potentially worsening a spill that left some birds coated with oil and has stirred worries about broader environmental impacts.

The cause of the pipeline break just offshore from Los Angeles remains under investigation. Early findings point to a ship anchor possibly catching the line and dragging it across the seafloor, tearing a gash in the half-inch-thick (12.7 millimeter) steel pipe.

The timeline of the company’s response appears to contradict statements from Amplify’s CEO, Martyn Willsher, who told reporters on Monday that the company first became aware of the spill after receiving a report from a boat of a sheen in the water.

Willsher acknowledged the company’s equipment was supposed to help detect spills, then said, “we did not have any notice that there was a leak” prior to the sheen report.

In documents released Tuesday detailing the company’s actions, federal transportation officials did not comment on the time lag in shutting down the line or reveal any potential explanation that the Amplify executives may have offered.

Company representatives did not respond to emailed questions about the delay between the alarm and the shutdown.

Problems with faulty leak detection procedures have plagued the industry for years, including during a massive 2010 oil spill that polluted 40 miles (64 kilometers) of Michigan's Kalamazoo River. In that case, an Enbridge Inc. pipeline leaked at least 843,000 gallons (3.2 million liters) of crude over 17 hours, even as alarms kept going off in a company control room.

The company later settled pollution violations in the case for $176 million.

The accident spurred calls for more stringent leak detection rules and the installation of more automatic or remote-control shut-off valves that can quickly halt the flow of oil in a leak.

A dearth of such valves was also cited in another 2010 pipeline accident — a natural gas transmission line explosion in San Bruno, California, that left eight dead and dozens injured after the line continued burning like a massive blowtorch for almost 90 minutes before the line was shut down manually.

Federal officials began crafting new leak detection and valve rules under former President Barack Obama, but they were never finalized.

A new rule proposed last year under former President Donald Trump and now awaiting final approval would mandate more valves only for new or replaced oil pipelines, not the thousands of miles that are already in use. The change came after oil industry lobbying groups including the American Petroleum Institute said retrofitting lines with valves would cost up to $1.5 million per device.

The pending rule does not set standards for leak detections, giving companies significant leeway in how sensitive to leaks their equipment needs to be, said Bill Caram with the Pipeline Safety Trust, a Bellingham, Washington-based group that advocates for safer pipelines.

“It makes us worry for our country's aging energy infrastructure,” Caram said. "We fear this could become a bigger and bigger issue."

John Stoody with the Association of Oil Pipe Lines said companies and industry groups are working hard to improve leak detection technologies. Fine-tuning equipment is part of that, to make sure companies can detect even small leaks but not have to respond to false alarms.

“If you're riddled with false alarms, people have a harder time reacting,” Stoody said.

Share:
More In Business
‘Chainsaw Man’ anime film topples Springsteen biopic at the box office
A big-screen adaptation of the anime “Chainsaw Man” has topped the North American box office, beating a Springsteen biopic and “Black Phone 2.” The movie earned $17.25 million in the U.S. and Canada this weekend. “Black Phone 2” fell to second place with $13 million. Two new releases, the rom-com “Regretting You” and “Springsteen — Deliver Me From Nowhere,” earned $12.85 million and $9.1 million, respectively. “Chainsaw Man – The Movie: Reze Arc” is based on the manga series about a demon hunter. It's another win for Sony-owned Crunchyroll, which also released a “Demon Slayer” film last month that debuted to a record $70 million.
Flights to LAX halted due to air traffic controller shortage
The Federal Aviation Administration says flights departing for Los Angeles International Airport were halted briefly due to a staffing shortage at a Southern California air traffic facility. The FAA issued a temporary ground stop at one of the world’s busiest airports on Sunday morning soon after U.S. Transportation Secretary Sean Duffy predicted that travelers would see more flights delayed as the nation’s air traffic controllers work without pay during the federal government shutdown. The hold on planes taking off for LAX lasted an hour and 45 minutes and didn't appear to cause continued problems. The FAA said staffing shortages also delayed planes headed to Washington, Chicago and Newark, New Jersey on Sunday.
Boeing defense workers on strike in the Midwest turn down latest offer
Boeing workers at three Midwest plants where military aircraft and weapons are developed have voted to reject the company’s latest contract offer and to continue a strike that started almost three months ago. The strike by about 3,200 machinists at the plants in the Missouri cities of St. Louis and St. Charles, and in Mascoutah, Illinois, is smaller in scale than a walkout last year by 33,000 Boeing workers who assemble commercial jetliners. The president of the International Association of Machinists says Sunday's outcome shows Boeing hasn't adequately addressed wages and retirement benefits. Boeing says Sunday's vote was close with 51% of union members opposing the revised offer.
FBI’s NBA probe puts sports betting businesses in the spotlight
The stunning indictment that led to the arrest of more than 30 people — including Miami Heat guard Terry Rozier and other NBA figures — has drawn new scrutiny of the booming business of sports betting in the U.S. The multibillion-dollar industry has made it easy for sports fans — and even some players — to wager on everything from the outcome of games to that of a single play with just a few taps of a cellphone. But regulating the rapidly-growing industry has proven to be a challenge. Professional sports leagues’ own role in promoting gambling has also raised eyebrows.
Load More